ProjeQtOr free project management software - How do I prorities a resource's work? - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How do I prorities a resource's work?

More
29 Mai 2019 09:29 - 29 Mai 2019 09:34 #1 by clarezoe
I'm using V.8.0.4.
As is shown in the next picture, the resource is working full time on project 4.2 (priority 500) from September.


And the resource is doing nothing on project 9.2 (priority 400) the last week of August but half time on project 4.2.


How should I do so that the resource works on project 9.2 and finish it in August and start full time on project 4.2 despite the fact that the resource is allocated from 1/9? You see that the priority on the project doesn't seem to work.

Thanks!
Attachments:
Last edit: 29 Mai 2019 09:34 by clarezoe.

Please Connexion or Create an account to join the conversation.

More
29 Mai 2019 09:38 #2 by clarezoe
A quick update. I removed the allocation and re-added it from September and it worked. Maybe you can have a look at it and see if it is a bug.
Thanks!

Please Connexion or Create an account to join the conversation.

More
29 Mai 2019 14:12 - 29 Mai 2019 14:17 #3 by alainforma
hi
your resource works in full time on this activity before september ?!

Nevertheless, if you want that your resource work on one project ( and its activities) and not another one, you can either play with priorities, or periods of allocation, or dependencies, or milestsones, or planification mode like " not start before validated start date " for the activitry which follows this one. In fact, your resource works on others activities without ending another one, it is just because " you play" with all this features. I can t find easily what you have done wtih just the few informations you get to us.
The software never goes wrong ;-)
Regards.
Last edit: 29 Mai 2019 14:17 by alainforma.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.056 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.