View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Should not end before validated date - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Should not end before validated date

More
03 Jui 2019 11:11 #1 by clarezoe
Hi,

I have an activity which has the planning mode "should not end before validated date", however the planning doesn't seem to work. What did I do wrong?
Attachments:

Please Connexion or Create an account to join the conversation.

More
03 Jui 2019 14:08 #2 by alainforma
Hello,
This software will attempt to respect the validated end date, but if a constraint exists elsewhere (generally the availability of resources that is insufficient) so it plans at the earliest but after the validated date because it indicates clearly the reality of things.
It means that is your job as Project Leader to find a solution to get what you want by modifying or cancelling constraints...

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.