View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Dependencies beetween tasks - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Dependencies beetween tasks

More
04 Sep 2019 09:06 #1 by JulioLep
Hello guys,
I created 2 tasks to make a test:
> Task A
> Task B with as successor of task A (End > Start + 5 days)
However in the planning view, the depedency does not apply (Please see attached)
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 09:18 #2 by alainforma
Hello,

It should be ! but...
Have you ever recorded some real work on B ?
Have you tryed to replan it ?

Regards.

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 09:23 #3 by JulioLep
Thanks for your quick reply, no there is no work recorded as I'm initializing the plan, so without work recorded the depedencies are not takken into account ?
Yes I put auto calculation of the planning.

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 09:49 - 04 Sep 2019 09:52 #4 by alainforma
Hi,

The start date of the bar is displayed according to the 1st day with work recorded on timesheet. By adding a dependence (predecessor) with ( or without) a delay, the remaining days could be pushed back in time, the bar would grow longer (without any changes about the start date due to real work).
On planning screen view, even if the cell "automatic run plan" is checked, changes are not taken into account when data come from another screens. You have to enable the calculation. On the contrary, if you work directly on the planning view, every changes are taken into account when the cell is checked.

what is the version you are using ?

Regards.
Last edit: 04 Sep 2019 09:52 by alainforma.

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 13:07 #5 by JulioLep
Ok I'll try and come back to you.
I'm using version 8.1.5

Please Connexion or Create an account to join the conversation.

More
04 Sep 2019 15:12 - 04 Sep 2019 15:13 #6 by alainforma
you are welcome, tell us please.
Last edit: 04 Sep 2019 15:13 by alainforma.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.