View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Organisation of QUESTIONS and DECISION into planning - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Organisation of QUESTIONS and DECISION into planning

More
20 Fév 2020 16:03 #1 by ashofphoenix
Hi,
- Is there a way to better organise Questions and Decisions into the planning ?

The problem is that I've got some specific "management" task in order to organise my planning but I can't put all questions decision into specific activity as it said it's impossible to move
(but Q/D still attached to project - Refer to attachment to see specific message)

- Is there also a way NOT to mix Q/D according to there ID into planning (see also attachment, a decision is put in middle of question without possibiliti to organise it
is there a way to make _#x (unity reference ID of question) appear BEFORE _#xx (decade reference ID of question) and not messing up everything ???)

Thanks for help
Attachments:

Please Connexion or Create an account to join the conversation.

More
24 Fév 2020 21:21 #2 by babynus
No.
Remember that Global Planning is just a way to "display" non plannable tasks.
You cannot organize these non plannable tasks like palanble ones.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
25 Fév 2020 08:26 - 25 Fév 2020 08:28 #3 by ashofphoenix
ok, i understand that i can't "organise" as a planned task and won't be able to move them elsewhere. However it should be obvious, as you can see them in planning with date of question//decision, to be able -at least- to see them well ordered and not messy as they are ! for example Questions First Then Decision and putting #_10 ID AFTER #_4 ID and not mixed up as there are now ???

Even without moving them onto a planned task, at least be able to move them from a line to another to fix the mess-up, staying at zero level (i.e. project tab and not any planned task)
Last edit: 25 Fév 2020 08:28 by ashofphoenix.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.