View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Planning calculation per week - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Planning calculation per week

More
26 Oct 2020 09:14 - 26 Oct 2020 09:30 #1 by QUANTAMEDICAL
Hello,

I would like to plan activities up to 5% of the total availability of my resources
But I would also like these activities to be done in half a day to avoid going too much from one subject to another.
So I assigned the collaborators to 5% on this project and indicate a minimum task threshold of 0.5 days.
While scheduling I have an error message telling me that the 0.5d cannot be scheduled because it exceeds the maximum capacity.

What I understand is that the planning is done per week: 5% of 5 days of W = 2 hours. Which is below the threshold of 0.5 days.
But yet I am not specifying that the 5% is in cycles of one week. we could therefore have imagined having a 0.5 day week, then nothing the following week, in order not to exceed the load over 1 month and not 1 week.

Also would there be an option to evaluate the assignment on the project by month and not by week?

many Thanks
Last edit: 26 Oct 2020 09:30 by QUANTAMEDICAL.

Please Connexion or Create an account to join the conversation.

More
28 Oct 2020 15:27 #2 by babynus
Yes, you put unresolvable contraints :
- 5% allocation to project : so not more than 0,2 per week
- 0,5 day threshold : cannot plan less than 0,5 per day
So you can never plan the expected 0,2 days...

You can possibly ghet what you expect with "regular between dates" planning more, or more precisely "regular in half days".
With this mode, you indicate start and end date : for instance "2021-01-01" to "2021-12-31" and then assign the resource for 5% of yealy availability (let's say 10 days per year).
This will plan 0,5 days from time to time, up to 10 days during the period
NB : you must allocate resource at 100% to the project.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.