View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Link Project Product & Product Version: closed state - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Link Project <> Product & Product Version: closed state

More
20 Mar 2021 01:25 - 20 Mar 2021 01:25 #1 by Tony44
Hi,

On a project, 'Configuration' section, we can link products and product versions.
On these links, it is possible to check a "closed" state, as below :

 

What are the expected behaviors / results when this box is checked :
- on the Project <> Product link ?
- on the Project <> Product version link ?

Is it expected that the product or version whose link to the project is closed is no longer available on the elements of the project ?
For example, the product version would no longer be offered in the 'original product version' and 'target product version' fields of a ticket for this project.
I see this is not the case, is this an issue ?

Thanks !

Tony44
Attachments:
Last edit: 20 Mar 2021 01:25 by Tony44.

Please Connexion or Create an account to join the conversation.

More
21 Mar 2021 13:56 #2 by babynus
Hi,

Thiks is entended to work as you describe.
It it doesn't it is an issue.
We'll have a look.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: Tony44

Please Connexion or Create an account to join the conversation.

More
22 Mar 2021 01:06 - 22 Mar 2021 01:21 #3 by Tony44
Ok, Thanks.

Likewise, the "start date" and "end date" fields of these links are not taken into account : the product and the product version are available outside the validity period of the link defined by these dates.

Tony44
Last edit: 22 Mar 2021 01:21 by Tony44.

Please Connexion or Create an account to join the conversation.

More
07 Avr 2021 23:02 - 07 Avr 2021 23:04 #4 by Tony44
Hi,

In V9.1.2, the closed link is now well taken into account.

However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates. 

Tony44
Last edit: 07 Avr 2021 23:04 by Tony44.

Please Connexion or Create an account to join the conversation.

More
09 Avr 2021 15:30 #5 by babynus

However, the “start date” and “end date” fields of these links are still not taken into account: the product and the product version are available outside the validity period of the link defined by these dates. 

These dates (displayed on project for linked versions) is not date for the link.
These are for information about dates of version. They have no impact on link availability.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
09 Avr 2021 23:56 #6 by Tony44
Alright, that's fine with me.
In fact I had understood the opposite in the user manual :
 

Tony44
Attachments:

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.076 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.