ProjeQtOr free project management software - calendars - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

calendars

More
03 Aoû 2021 18:26 - 03 Aoû 2021 18:29 #1 by chaours
calendars was created by chaours
calendars I have an activity which is carried out during the week and one which is carried out on weekends I created 2 calendars a classic (the one by default day absent Saturday Sunday) and a "weekend" calendar where only Saturday and Sunday are worked but how affected them to the spots?
***
les calendriers

J'ai une activité qui s'exerce en semaine et une qui s'excerce en week-end j'ai créé 2 calendriers un classique (celui par défaut jour chomé samedi dimance ) et un calendrier "week-end" où seul le samedi et le dimanche sont travaillé

mais comment les affecter aux taches ? 
Last edit: 03 Aoû 2021 18:29 by chaours.

Please Connexion or Create an account to join the conversation.

More
04 Aoû 2021 09:31 #2 by Arkhanje
Replied by Arkhanje on topic calendars
Hello,

Calendars are associated with resources, not tasks.

Please Connexion or Create an account to join the conversation.

More
04 Aoû 2021 10:17 #3 by chaours
Replied by chaours on topic calendars
ok so it is impossible to attribute to a resource activities only the week and only the weekend or is there a solution?

***
ok donc c'est impossible d'attribuer à une ressource des activité uniquement la semaine et uniquement le week-end ou bien y a t il une solution ?

Please Connexion or Create an account to join the conversation.

More
04 Aoû 2021 11:59 - 04 Aoû 2021 12:05 #4 by Arkhanje
Replied by Arkhanje on topic calendars
A resource can effectively only have one calendar.

There are still a few workarounds.
You start by unchecking non-working days in the global parameters so as to have all the days of the week that can be planned.

you go through the absence table to manually indicate the unavailability according to your choices.
or
you create two resources to represent one, each with a different calendar. (Be careful however with the planning modes so that this resource is not scheduled 7/7)
or
you use the planning modes
or
you can play with the periods of assignments to projects

I am thinking of these but there may be others. If some users have other solutions, do not hesitate!
Last edit: 04 Aoû 2021 12:05 by alainforma.

Please Connexion or Create an account to join the conversation.

More
03 Mai 2022 09:17 #5 by Coasterman
Replied by Coasterman on topic calendars
It would be handy if a calendar could be assigned by period similar to variations in resource capacity (or extend it with the calendar).
Another solution (which would avoid manipulating resources) could be to add a calendar choice possibility to the progress section planning modes.

E.g., when it would be handy to have such posibilities:
1) If someone is for commissioning in a country with different calendar system and different holidays it is a nightmare to use manual planning (or there is a shortcut to mark multiple days at once and not single days) .

2) Currently all this Corona quarantines. Sepending on traveling dates they start/end on weekend days you want to set to set 14 days but you need to know exactly the capacity and everything.

3) if someone has to work on different shift for a certain time. e.g. August to November only on 3 days, in june on weekends etc.

Please Connexion or Create an account to join the conversation.

More
03 Mai 2022 23:58 #6 by babynus
Replied by babynus on topic calendars

It would be handy if a calendar could be assigned by period similar to variations in resource capacity (or extend it with the calendar).
Another solution (which would avoid manipulating resources) could be to add a calendar choice possibility to the progress section planning modes.

It is quite complex to do and covers very specific need, so we won't spend time on this unless the evolution is sponsored.

Maybe solutions could be 
  1. Have a specific calendar for resources in that case
  2. Have calendar without off days, andd manage all off days through "absence" 

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.