View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - assignment in assignment form and sure in date and duration? Hello, I can't f - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

assignment in assignment form and sure in date and duration? Hello, I can't f

More
04 Aoû 2021 11:10 #1 by chaours
assignment in assignment form and sure in date and duration? Hello, I can't figure out what to do in this case: for example for a project I am alone to do the stains, and for example a stain that would last 4 days Do I have to put 4 days in "validated duration" or in the assignment sheet "assigned work" or in both? thank you

***
assignation dans fiche assignation et surée dans date et durées ?
 bonjour,

je n'arrive pas a comprendre ce que je dois faire dans ce cas :

par exemple pour un projet je suis seul pour faire les taches, et par exemple une tache qui durerait 4 jours
est ce que je dois mettre 4 jours dans "durée validé" ou dans la fiche d'assigantion "travail assigné" ou bien dans les deux ?
merci

 

Please Connexion or Create an account to join the conversation.

More
04 Aoû 2021 11:44 - 04 Aoû 2021 11:52 #2 by alainforma
hi

4 days assigned is the real workload planified respecting the mode of planification you ve choosen. 4 days validated is just an information ( an estimation )on what you expected - you expect or you will expect to spend on it. assigned and valided are not systematically identical, of course. Moreover, i like to specify that steering by duration or by woarkload do not give the same outcomes. By the way, you will steer as you want projeqtor allowing both of them.
Projeqtor is on a dynamic way to planify, it means the planification will be done depending on all constraints you give to it ( resource'scalendar for instance and so on as we start to count hereby).
Last edit: 04 Aoû 2021 11:52 by alainforma.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.