View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - progress of an activity how to inform the progress of an activity I have read a - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

progress of an activity how to inform the progress of an activity I have read a

More
12 Aoû 2021 17:09 #1 by chaours
progress of an activity how to inform the progress of an activity I have read and reread the manual I can only find descriptions of the panels but I cannot understand how to inform in the steering section the percentage of progress ...? Thanks for your feedback.
****
progres d'une activité

comment faire pour renseigner le progres d'une activité j'ai lu et relu le manuel je ne trouve que des description des panneaux mais je n'arrive pas à comprendre comment renseigner dans la section pilotage les pourcentage d'avancement ... ? merci pour votre retour.

Please Connexion or Create an account to join the conversation.

More
12 Aoû 2021 17:36 #2 by babynus
Projeqtor is work driven (effort driven) : when you enter real work, progress is updated.
You can also activate "manual progress for fix duration activities" is global parameters if you don't want to manage real work

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
12 Aoû 2021 17:51 - 12 Aoû 2021 17:55 #3 by chaours
ok thanks but it's grayed out in the real box

ok merci mais c'est grisé dans la case réel
Attachments:
Last edit: 12 Aoû 2021 17:55 by chaours.

Please Connexion or Create an account to join the conversation.

More
12 Aoû 2021 18:02 #4 by babynus
Real work must be entered through timesheet

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
12 Aoû 2021 18:15 #5 by chaours
thank you for this feedback, and "manual progress for fix duration activities" where should we enter it?

***

merci pour ce retour, et "manual progress for fix duration activities" où doit on le rentrer ?

Please Connexion or Create an account to join the conversation.

More
13 Aoû 2021 09:10 #6 by alainforma
global parameters / activity / planning / The fourth line.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.041 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.