View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] automatic user rights assigment following contract (or project) validity - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] automatic user rights assigment following contract (or project) validity

More
31 Aoû 2021 14:39 #1 by CPruvost
Dear community,

I would like to know if it would be anyhow possible :
- to allow the users who are contacts for a customer to create ticket only if a given contract (or project) with this customer is still open (and to disable ticketing from the users if the contract is closed).
OR
- to set automatically the users who are contacts for a customer as closed if a given contract with this customer is closed.

Many thanks for your input !

Please Connexion or Create an account to join the conversation.

More
01 Sep 2021 12:49 #2 by Arkhanje
Hello

yes it is possible, depending on their rights assigned to the project it should be sufficient.

In fact, user rights are assigned by project.
You do one project per client, when the contract is completed you close the project in question and the contacts, users, resources linked to this project will no longer have access to the data even if they retain the right of entry to your session.
The following user(s) said Thank You: CPruvost

Please Connexion or Create an account to join the conversation.

More
01 Sep 2021 14:41 #3 by babynus
Hi,

No, there is no way to automatically manage rights depending on a contract.
You'll have to manually change rights (close allocations)

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: CPruvost

Please Connexion or Create an account to join the conversation.

More
02 Sep 2021 09:17 #4 by CPruvost
I understand it is not possible as such, but I can create a project corresponding to the contract and close it when the contract is finished. At least it closes all the connected account linked in a go (if numerous).
I might use this, and create a project per product and a sub-project per contract.
Automation would be an interesting future feature though.

Many thanks !
The following user(s) said Thank You: Arkhanje

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.037 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.