View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Dependencies linking between activities - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Dependencies linking between activities

More
27 Avr 2022 08:56 #1 by navver1990
Dear Sir/Madam,

This question is regarding dependencies linking and baselining the planning.
The issue faced by me during project planning and linking is "
after the dependencies linking , whether the linking of dates will be aligned as per the
planning". So I have performed following test case to verify it:

created new project "Test scheduling"
created 4-5 activities and provide start date , allocate resource, enter BL effort.
On validating/baselining nothing happened like change in dates etc. Though i can see my
linking in gantt chart as per the baseline.But the dates are not changed for activities as per the dependency
for activities

So for all the activities,manual Baselined start date and end date need to be filled.According to my view,after initial baselining and as per dependency
dates should get filled automatically for predecessor and successor activities as per reference date.

Thanks,
Naveen

 

Please Connexion or Create an account to join the conversation.

More
27 Avr 2022 09:48 - 27 Avr 2022 10:17 #2 by Arkhanje
Which dates do not change? validated? planned?
These dates do not change but when do you do what exactly?
What do you mean by "On validating/baselining" because the baseline and validating the planning are not the same thing.

According to my view,after initial baselining and as per dependency
dates should get filled automatically for predecessor and successor activities as per reference date.

And we have the possibility of recovering the planned dates towards the validated...
try to describe as well as possible, with the ProjeQtOr vocabulary (exact name of the functions used, screenshots... so that we can identify the steps you are doing.



Try reading these very interesting passages from our manual, which you can find online or by pressing F1 directly from your session!

Dates and duration
Planning validation
Baseline
Dependencies
Last edit: 27 Avr 2022 10:17 by Arkhanje.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.