ProjeQtOr free project management software - Manual set of activity progress - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Manual set of activity progress

More
18 Mai 2022 16:29 #1 by LaurentC
The progress bar is clamped to 0% whatever I set in the manual progress field.
Do we have to assign a dummy guy ? What dis I miss ?
Thanks in advance.
Here are my settings for the relevant task:

Global parameters / planning: set "manual progress of fixed-duration activities" to "yes"
Activity screen:
• treatment tab: Fix planning = checked
• Progress tab:
  Technical progres section:
    set progress to manual.
    fill in the progress percentage.
  steering section:
    planning = fixed duration
    fix planning = checked

 

Please Connexion or Create an account to join the conversation.

More
19 Mai 2022 09:13 #2 by Arkhanje
Hello, 

Manual progress is entered in the processing tab in the management section. You have a progress field that you can modify manually and this on activities in "fixed duration" planning mode.

The box you check "fix the planning" prevents any changes to your activity. Whether it's in the treatment or advancement section. It is never recalculated. Read the tooltips carefully when in doubt.

As for the technical progress, it is to follow the progress of your work units. Fill in a catalog beforehand... nothing to do with what you want to do.

Just in case, the manual is accessible from your session by pressing F1

Please Connexion or Create an account to join the conversation.

More
19 Mai 2022 10:00 #3 by LaurentC
Thanks a lot for your reply.
1) Therefore I just have to consider the Progress Tab / Steering section and set the activity to fixed duration. And it should work with "fixed planning" and non "fixed planning" activities and with  "fixed planning" and non "fixed planning" projects
Is my understanding correct ?
2) Thanks to your help, I have now a correct progress bar for the activity, with progress set manually.
PROBLEM: no effect on the parent activity (which is a phase), and no effect on the project progress.

Thanks a lot.
#L.

Please Connexion or Create an account to join the conversation.

More
19 Mai 2022 18:01 #4 by babynus
To get Manual Progress, you must 
 - activate the option in global parameters
 - set planning mode a "fixed duration"
 - not add assignments
 - add validated work to the activity
Then progress can be manually entered
Then progress is displayed on bar.
Then progress is consolidated to parent (validated work is then used to get the "weight" of the sub-activities)
 

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: LaurentC

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.