View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Creating projects before the current date for archive purpose. - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Creating projects before the current date for archive purpose.

More
02 Jui 2022 22:17 - 02 Jui 2022 22:19 #1 by Marty
Hello,
We are trying to insert some of our previous projects into ProjeQtor and I'm having trouble with the start date. 
We're doing this for reference purpose and also to have a track reccord of our developpement work. 

When I insert a start date of January 1st 2021, the start date defaults to today's date.  
Is there a way to force the system to accept Project structures (Project' Activities and expenses, etc)   before the current date? 
Thanks :-)
 
Attachments:
Last edit: 02 Jui 2022 22:19 by Marty.

Please Connexion or Create an account to join the conversation.

More
03 Jui 2022 09:06 - 03 Jui 2022 09:06 #2 by Arkhanje

 Is there a way to force the system to accept project structures (project activities and expenses, etc.) before the current date?


yes of course you can use some schedule modes, dependencies and milestones, also you can use the start date setting on the project.


Don't hesitate to take a look here!
Planning modes
Milestones
Global Parameters - Planning
Last edit: 03 Jui 2022 09:06 by Arkhanje.

Please Connexion or Create an account to join the conversation.

More
03 Jui 2022 14:59 #3 by Marty
Thanks for the references.  It will be helpfull.  

I did some digging last night and I think I found a way to do this. 
I changed the parameter : Do not start before validdated date to NO

Then I entered : IN PROGRESS date and DONE date.
This seems to give me the result I want.

My next step will be to import the Activities by EXCEL table in the same manner and I should have my archived project structure.  I will also have to look at including the Assigned, real and left work for cost calculations. 

Thanks

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.039 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.