View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Impossible to leave "manual" planning mode as some "real" planning exists - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Impossible to leave "manual" planning mode as some "real" planning exists

More
24 Jui 2022 14:07 #1 by LaurentC
Hi,
In activity, I would lik to leave the manual planning mode, but I got this message.
However, I don't see any real planning for this activity (planned dates are grey and empty).
Also, why manual progress is limitated to fixed duration ?

Thanks in advance

Please Connexion or Create an account to join the conversation.

More
24 Jui 2022 14:11 #2 by alainforma
HI,

Which message ? ( not attached)
What the meaning of the last sentence ? Do not understand.

Please Connexion or Create an account to join the conversation.

More
24 Jui 2022 14:17 #3 by LaurentC
The message is impossible to leave "manual" planning mode as some real planning exists.
Concerning the last sentence, it seems that the setting manually the progress of an activity is limitated to fixed duration planning mode. But why this limitation ?
Thanks in advance. 

Please Connexion or Create an account to join the conversation.

More
24 Jui 2022 14:26 - 24 Jui 2022 14:27 #4 by alainforma
Sorry, but i still do not undersand your request about tthe link beetween, progress,  planning mode and fixed duration. Could you explain again. Thank U;
Last edit: 24 Jui 2022 14:27 by alainforma.

Please Connexion or Create an account to join the conversation.

More
24 Jui 2022 14:32 #5 by LaurentC
Fixed duration is one of the available planning mode for activities.
Setting the planning mode to fixed duration is mandatory to set manually the progress of the activity. But why such a limitation ? Why this feature is not available in manual planning mode for instance ?

 

Please Connexion or Create an account to join the conversation.

More
24 Jui 2022 15:38 - 24 Jui 2022 16:12 #6 by alainforma
What is your matter ? Yes on fixed duration the progress could be calculated "manually" based on valided cost  or are you talking about the fact that progress  is calculated depending on the duration if no workload had been given ? On first case, you can integrate the progress of this single activity which  you do not master ( supplyer, another office, another team, ...) on your whole progress of the project to get a better real value than none.
On manual planning progress is only  calculated depending on the workdone compare to the whole one ( done + left) cause you have given and planified real workload by your own because you master ( you manage)  this activity.
Last edit: 24 Jui 2022 16:12 by alainforma.
The following user(s) said Thank You: LaurentC

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.032 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.