View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Schedule activities - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Schedule activities

More
09 Jui 2023 13:35 #1 by FAD
Schedule activities was created by FAD
Hi,

I don't understand why, is it impossible to assign time to my resource.
The resource is free this day (14/06/23), but the system message indicate that it'is impossible to plan the job because  the left time is not enough.

I'm surprise, something seems is wrong, but why ?

I have try to put the rate to 0%, but it still wrong...

Many thanks for your help,

Fred


 
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Jui 2023 13:55 - 09 Jui 2023 13:57 #2 by alainforma
Replied by alainforma on topic Schedule activities
HI,
Have you also checked if a period has been allocated of this resource on this project ?
Have you thought to replan the planning ?
Last edit: 09 Jui 2023 13:57 by alainforma.

Please Connexion or Create an account to join the conversation.

More
09 Jui 2023 14:31 #3 by FAD
Replied by FAD on topic Schedule activities
Hi,

Many thanks for your reply..

I didn't have end date of project. I have put end date date of project, but still the same behaviour..

I can't plan the job. It's the first task created on my project, and any task are planned.

Please Connexion or Create an account to join the conversation.

More
09 Jui 2023 15:20 #4 by alainforma
Replied by alainforma on topic Schedule activities
I asked you if your resource is allocated on projet with a limited period ?

Please Connexion or Create an account to join the conversation.

More
09 Jui 2023 15:37 - 09 Jui 2023 15:39 #5 by FAD
Replied by FAD on topic Schedule activities
Yes my resources is allocatedto the master project.

My project is sub project from another.

If the ressource will not available for the project, it' will be impossible to assign to the task.
Attachments:
Last edit: 09 Jui 2023 15:39 by FAD.

Please Connexion or Create an account to join the conversation.

More
09 Jui 2023 15:51 - 09 Jui 2023 15:53 #6 by alainforma
Replied by alainforma on topic Schedule activities
Be careful the rate is 0 on your pic below ; give a value and then ?
ok the limited period is good in our case
Last edit: 09 Jui 2023 15:53 by alainforma.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.080 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.