ProjeQtOr free project management software - How to export / import & replace assigments? - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How to export / import & replace assigments?

More
16 Jan 2024 17:06 #7 by brasal
Thank you Plucks, but it does not seem to allow to export all the details, I mean workload assigned/remaining per activity and per resource with percentage of the resource for each activity ?

Please Connexion or Create an account to join the conversation.

More
17 Jan 2024 09:02 #8 by Arkhanje
Hello 

Indeed, the assignments screen does not allow you to see the percentage of the load per resource on each activity.
But we can produce the report that would best suit you to have this information. Do not hesitate to contact us via the contact form to obtain a quote quickly ! 

Please Connexion or Create an account to join the conversation.

More
17 Jan 2024 10:18 #9 by brasal
Hi,
I recall my need: being able to export then import assignments into projeqtor in the way that all assignments are defined in a csv or Excel or JSON or else file at export and they replace enterely the ones inside the projeqtor project at import. My use case is to be able to work on assignments outside of ProjeQtOr with some AI algorithms. So I need in this export/import process all the details. Moreover, mathematically, if I don't change the assignments of workload per activity and per resource nor resource availability, the project state in ProjeQtOr should remain unchanged (Export o ID o Import == ID).

Please Connexion or Create an account to join the conversation.

More
22 Jan 2024 14:58 #10 by babynus
Just export assignments with IDs.
Change data then reimport files with preserved IDs, assignments will be overwritten.
Note that some fields that are calculated by ProjeQtOr will not be imported (plannedStartDate, plannedEndDate, notPlannedWork,...).

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: brasal

Please Connexion or Create an account to join the conversation.

More
22 Jan 2024 16:05 #11 by brasal
Great, thank you. It would be nice to authorize planned dates import (to be used with manual planning calculation in order to disengage this one). This improvement would enable worthy openings to external home made engines.

Please Connexion or Create an account to join the conversation.

More
22 Jan 2024 16:17 #12 by brasal
This rises the additional question: Does the "resource planning calculate" feature computes from scratch or from the "activity planning calculate" feature last results?

I can imagine that for ergonomy reasons you choosed the first, while for the use of an external engine I would need the second solution where I don't want ProjeQtOr to modify the planned dates anymore.

A global checkbox to freeze the planned date might then be a quick-win solution.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.