View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Cash Flow Plan - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Cash Flow Plan

More
02 Mar 2025 18:22 #1 by kishorevenki
Cash Flow Plan was created by kishorevenki
Hello,
I am looking for how to organize and track the cash flow to the vendor . 
For example, for the below tasks
10% advance for the supply of materials ph-1  - $5000/-  Planned date - 30th March
30% for the supply of materials for Ph-1 - $8000 , Planned date - 30th April
10% advance for the supply of materials ph-1  - $5000/-  Planned date - 15th April

These activites are defined in planning. But how to specify the cost details. Further based on the above example, I should pay to the vendor  in March - $5000, April - $13000. 
Please advise how to create cash flow table whist defining the various tasks in Planning. 

Regards,
Kishore

Please Connexion or Create an account to join the conversation.

More
03 Mar 2025 10:33 - 13 Mar 2025 09:32 #2 by Arkhanje
Replied by Arkhanje on topic Cash Flow Plan
Hello

You can create terms in the expense financial module . I invite you to read the manual on this part.

The project type must be suitable for processing terms dates. For example, on a project type  fixed price .
In the provider invoices you have a section that processes terms .
Click on the + and you will be able to set the percentages to be invoiced, as well as the dates of the total amount.

 
Attachments:
Last edit: 13 Mar 2025 09:32 by Arkhanje.
The following user(s) said Thank You: kishorevenki

Please Connexion or Create an account to join the conversation.

More
03 Mar 2025 10:49 #3 by kishorevenki
Replied by kishorevenki on topic Cash Flow Plan
Thanks for the response.
But I would like to link the dates based on the planned dates instead of manually entering the dates. Similarly while monitoring if the dates are skipped, payment would also be delayed.
How to link the planned dates of task / milestones to the payment dates?

Please Connexion or Create an account to join the conversation.

More
03 Mar 2025 11:36 #4 by Arkhanje
Replied by Arkhanje on topic Cash Flow Plan
No, we can't do that right now, but you can contact us for possible sponsorship

Please Connexion or Create an account to join the conversation.

More
11 Mar 2025 12:16 #5 by kishorevenki
Replied by kishorevenki on topic Cash Flow Plan
Hi,
As you suggested I have created provider order and terms. Through terms, orders, invoices, multiple payment schedule can be captured. But when we see the report under COST or FINANCIAL, the line items in the terms are not displayed.
In the resource cost repoort, A cross-tab report comprising the project name, Activity name and cost for each month is nicely available.
But for the expense report, only Project name is displayed and further only the total expense amount is mentioned. As per your example, the report shows only $18000 for Server, whereas multiple terms ($5000 , date1; $13000 - date2) is not visible.

Please let me know how to get the crosstab report (Cash flow report) based on the multiple payment terms.

Thanks....

Please Connexion or Create an account to join the conversation.

More
13 Mar 2025 11:15 #6 by Arkhanje
Replied by Arkhanje on topic Cash Flow Plan
Hi,

In your example, the report only displays $18,000 for the server, while the multiple conditions ($5,000, date 1; $13,000, date 2) are not visible.


It generally makes sense not to mix apples and oranges; the itemized details correspond to the invoice details.
The terms dates are simply a division of this amount for payment. Therefore, they will not appear on a cost or expense report, but on a terms schedule or payment report.

Could you tell me how to obtain the pivot table (cash flow report) based on the different payment terms?

Very simple, contact us and request a quote to create your report perfectly! 

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.082 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.