View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How to update the progress of a task which does not have resource assigned - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

How to update the progress of a task which does not have resource assigned

More
16 Avr 2025 16:57 #1 by kishorevenki
Hi,
I have created a task say
  • Delivery of the materials 
    • Planning mode - ASAP
    • No resource assigned
    • Duration - 40d
    • Validated start - 31st March
But on 10th Aprilm I came to know that the materials will be available on 16th April. I dont want to change the duration at that point of time, because I want to compare the actuals with baseline dates. Further since there is no resource assigned, timesheet cannot be used to enter the actuals. 

Kindly advise. 
Regards,
Kishore

Please Connexion or Create an account to join the conversation.

More
17 Avr 2025 11:26 - 17 Avr 2025 11:30 #2 by alainforma
Hello,

Your question is how to update the progress of this activity. OK.
So my question is how do you do to follow the progress before this modification of date ?
In fact, it seems difficult to calculate a progress without data workload. Alternatively, you can continue to use a rule of three to personally assess the progress calculated over different timescales.
Perhaps I don't fully understand your concerns so my answer at this point is : The progress depends on your own calculation then written down into a textual area.
Otherwise, use the functionnality "BASELINE" to keep a photo of your project with this activity you can compare later with your current Gantt. 
Best regards
Last edit: 17 Avr 2025 11:30 by alainforma.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.030 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.