Hello, I have parent activities linked to various projects. I also have a product evolution roadmap (an activity within a Roadmap project), and I would like to attach activities from other projects to it without breaking my current activity management structure.I’m not sure how to categorize activities from different projects so that I could ultimately obtain a status or report showing the total time spent on the product evolution roadmap.Is this possible?It’s almost as if an activity could have two parents:
the parent from my current activity structure, and
It’s almost as if an activity could have two parents:
Sure this is not possible.
whatever the tool, an activity can have only one parent.
Possibly you can link your activities to Product Versions, then use Version planning or Versioning reports.
I'm not sure you'll get what you expect but it may be a goiod stat.
Otherwise you can define a tag for same roadmap activities and restrict list of activities by tags.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.