I have an activity that was planned in "as soon as possible" mode (planned start and end dates are set, real dates are set also).
I want to reset these dates and switch to manual planning for the activity, to set planned dates according to validated dates.
What I do is check the "paused" tickmark, save, switch to "manual planning", save, untick "paused", "calculate planning".
But this does not work. Planned dates are never resetted, validated dates are never taken into account.
hi
"planned start and end dates are set, real dates are set also". : which one planified or validated ? Real start dead ok Real end date is already filled ?
ANYWAY :
To plan manually go to this planification mode and use it. Fill all days long into the opened popup board as long as yours expected validated dates and then recalculate your project.
You can not realize your process as written : plan manually and automatically as validated dates are given : It is impossible.
En poursuivant votre navigation, vous acceptez le dépôt de cookies tiers destinés au bon fonctionnement et à la sécurisation du site (gestion de session, reCaptcha) et à une analyse statistique anonymisée des accès sur notre site (Google Analytics). Si vous vous inscrivez, les informations que vous fournirez ne seront jamais divulguées à un tiers sous quelque forme que ce soit. En savoir plus
Paramétrages de cookies
×
Cookies fonctionnels
Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.
Session
Veuillez vous connecter pour voir vos activités!
Autres cookies
Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.