ProjeQtOr free project management software - Duration of tasks - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Duration of tasks

More
12 Avr 2012 16:14 #1 by rigolint
Duration of tasks was created by rigolint
Hi everyone,

I would like to know how can I fix the duration of one activity ? At the creation of this one, someone is affected to this activity. I would like to set the requested duration and be warned if this person work more than it was scheduled.

If I set the requested duration at 3 days. If the person puts into the real work allocation 4 days, today, I do not have this information.

The task is planned as soon as possible.

The only way I find to be alerted is to define a end validated date but I do not want to do like this because if I want floating activities. I do not succeed in with the fix duration. Is there something I miss ?

Thanks a lot for your help.

Best regards.


Thomas

Please Connexion or Create an account to join the conversation.

More
12 Avr 2012 18:23 - 12 Avr 2012 18:23 #2 by babynus
Replied by babynus on topic Re: Duration of tasks
You mismatch duration and work.

That's not the same.
If you set duration, you won't have any alert on work.
Moreover, alerts are base on validated or assigned values, not requested ones.

What you need is to set assigned work and define an indicateor on 'planned work compraed to assigned work'.
Just when the resource updates left work to have planned work > assigne work, you'll be alerted.

Babynus
Administrator of ProjeQtOr web site
Last edit: 12 Avr 2012 18:23 by babynus.

Please Connexion or Create an account to join the conversation.

More
13 Avr 2012 09:42 #3 by rigolint
Replied by rigolint on topic Re: Duration of tasks
Hi,

Thanks for your answer.

I'm not sure it is sufficient. With your idea, I will be alerted if the person work more but I will not be alerted if the person does not work. How can I do this ?

That's why I want to be alerted for the global duration of the task.

Have a nice day.


Thomas

Please Connexion or Create an account to join the conversation.

More
13 Avr 2012 14:03 #4 by babynus
Replied by babynus on topic Re: Duration of tasks
I resource does not work on the task, then duration may not be changed : the resource will start later, but duration may not be changed.
The only sure value that will de changed is the planned end date (changed on planning calculation).
So you can use the corresponding indicator (planned end date compared to validated end date)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.033 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.