ProjeQtOr free project management software - Planned start and end dates - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

15 et 16 avril 2025 (9h-12h30)

14 et 15 mai 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

23 et 24 avril (9h-12h30)

20 et 21 mai (9h-12h30)

 

 

 

Planned start and end dates

More
26 Avr 2012 17:51 #1 by Mpoly
Hi,

What are the constraints for the planned start and end dates and how are they calculated.

I have a case where the planned duration is different from the planned end (minus) planned start. However, the data shown in the GANTT diagram is correct.

And how can we explain the planned end date is different from the validated end date.

Thanks for your help.
Attachments:

Please Connexion or Create an account to join the conversation.

More
26 Avr 2012 21:28 #2 by babynus
When planning mode is "as soon as possible", validated start and end dates are only references (for instance to generate alerts). Planned values are result of planning calculation.

To consider your case : start date is constrained by dependency (predecessor task) and end date only by resource availability. End date is correct. But strangely duration is wrong : I'll have a look, it may be an issue.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
27 Avr 2012 15:29 #3 by Mpoly
Thanks.

But still I can't understand why is the planned end date for the 22/05. The ressource used does't have any other affectation for the same periode. The point also is that when I affect another resource, the planned end date will be 25/05 and the calculated and shown planned duration is correct. How can we explain it. See 1st attached.

However, after making the calculation and then saving the activity, while affecting the 1st resource, I can get the correct result: P. duration = P. End - P. Start, but I can't understand why. see 2nd attachement.

Thanks for your help.
Attachments:

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.