Cheminade wrote: I expect a new version may be able to enter the time directly in the activity or the schedule of the person. Projector is a great tool and I discovered that I just put up in my service. The only flaw is the Skipping the schedule page to the capture page time and it is not easy to navigate this page when the person thirty tasks to be carried out two months to come.
Hi, I'm not sure I understand clearly what you do.
Do yu enter directly work in the "real wolrk allocation" (imputation) screen ?
If so, this screen is not done that for.
Way to work is :
- assign a resource to an activity for some defined work : you then get assigned work, real work (=0 at the begionning) and left work=assigned work.
- then you use planning to calculate best way to plan activity work. You can play with dependencies, priorities, planning mode and WBS to fit the planning to your needs.
- then each resource, day by day (or at least once a week) enters real work in the allocation screen, and re-evaluates left work (this is the key to good planification)
- then project leader just has to recalculate planning to get new target.
I guess it's not the way you use the tool, so maybe screen ergonomics is not adapted.