ProjeQtOr free project management software - How to use planning - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

How to use planning

More
20 Mar 2013 16:11 #1 by smatringe@yahoo.fr
Hello,

I defined a project with several tasks, each task is assigned to a ressource, as a duration and predecessor.

Now I would like to evaluate the estimate time of delivery of my project so i look in the Gantt (icone planning) it seems the gantt does not take into account predecessor to set the appropriate start date for each task.

When I click on "calculate activities planning" I am not able to select My project. I type its name in the combo but calculation does not have effect. I do not know what I missed in the configuration. Does somebody help please?

regards
Stephane

Please Connexion or Create an account to join the conversation.

More
20 Mar 2013 23:11 #2 by babynus
Replied by babynus on topic Re: How to use planning
Project'Or RIA is effort driven based : you must enter some assigned work.

RTFM

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
21 Mar 2013 07:56 #3 by smatringe@yahoo.fr
Thanks for your answer.

I do not understand where I have to define the assigned work? Currently I have define the duration and the resource on each task but I understand it is not enough.

I do not want to boring to much with so question but if you could give me a link to a tutorial explaining the different steps to full fill in order to have project or ria calculating a planing it will be fine. Currently the tutorial I found just give the definition of the object.

best regards
Stephane.

Please Connexion or Create an account to join the conversation.

More
21 Mar 2013 08:15 #4 by smatringe@yahoo.fr
Hi again,

In the tasks i finally define the "validated" start date,end date and duration instead of the requested and I got few results in planing calculation. Is it the good way to work?

What is the difference between Requested and Validated finaly from project or ria point of view?

regards
Stephane

Please Connexion or Create an account to join the conversation.

More
21 Mar 2013 09:25 #5 by babynus
Replied by babynus on topic Re: How to use planning

In the tasks i finally define the "validated" start date,end date and duration instead of the requested and I got few results in planing calculation. Is it the good way to work?

No, you need to add assigned work. The tool will then plan left work. (use planning button)

What is the difference between Requested and Validated finaly from project or ria point of view?

Requested = wished by customer (sometimes look like wish list ot Santa Klaus).
Validated = agreed (contractual)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.034 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.