View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Real work allocation - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Real work allocation

More
07 Mai 2013 10:07 #1 by Nic
Real work allocation was created by Nic
Hello everyboby, I did a search but I did not find a topic releated to my issue.
Ok, I need to know if there is an option that "automaticaly" keep trace of the work made by resurces.
Exe: I have a miller, he works 8 hours per day. The project he works on last 16 hours. I would like not to update every single day if he has worked on the project but just if the work was done after 16hours. In the same time I would like to see the progress bar of the work constantily updated by the system ,basically after 8 hours the system should say that the project is 50% complete.

I hope to have been clear.

Thanks a lot

Please Connexion or Create an account to join the conversation.

More
07 Mai 2013 12:05 #2 by babynus
Replied by babynus on topic Re: Real work allocation

I need to know if there is an option that "automaticaly" keep trace of the work made by resurces.

Not a trace like history on items, but you can check real work input on screen "real work allocation" and validate work for a given week (this will fix work)

The project he works on last 16 hours

A Project 2 days long : very very small project indeed :blink: . Better manage it as an activity... :whistle:

I would like not to update every single day if he has worked on the project but just if the work was done after 16hours

Just check the project progress.

In the same time I would like to see the progress bar of the work constantily updated by the system

Just have a look at Gantt planning view ;)

basically after 8 hours the system should say that the project is 50% complete.

It does : it is just called progress :whistle:
But of course, the resource must enter his real work in the tool, and possibly re-evaluate left work : the tool will not guess and read on one's mind :evil:

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
30 Sep 2013 09:53 - 30 Sep 2013 09:54 #3 by climb4fun
Replied by climb4fun on topic Re: Real work allocation
Hi,

basically after 8 hours the system should say that the project is 50% complete


may be an important hint for you:

There are two "progress" values:
1. progress = real work / planned work * 100
2. exepected = real work / valided work * 100

Difference is, one is planned progress and validated is progress on approved work/budget.

Regards,

Klaus
Last edit: 30 Sep 2013 09:54 by climb4fun.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.035 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.