ProjeQtOr free project management software - supervisor not view planning and Resource Planning - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

supervisor not view planning and Resource Planning

More
10 Mai 2013 16:52 #1 by pocampo
Greetings.

I have the following queries:


1. - I have defined profiles Administrator, Supervisor and Project Leader. In a test project, the Admin and Project Leader can see the Planning and Resource Planning, but the Supervisor can not see, why?. I tried placing the supervisor as a resource or project manager and can not see the planning. Deputy images.








2.- How can you incorporate this week working in planning?
Monday to Thursday: 8:00 to 13:00 14:00 to 19:00 10 hours daily
Fri: 8:00 to 13:00 hrs working 5

3.- In my team we have double functions (eg ing. A and Mr. B) depending on the project. In a project A can Ing To be leader, while I can be a project B only member. When defining the profile of this:
     Mr. A. Project Leader

In project A, you can change everything about your project.
In project B, you can change the same. When it should only do so in the assigned task.

I think I should define:

Eng A1. Proyeto Leader
Ing A2. Member of project

Both with the same contact email, and the user must enter second corresponds.Am I right?
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Mai 2013 17:52 #2 by babynus
1) It all depends on access rights.
Planning will gest visibility set to Activity in "Access mode to data screen"
=> The default access profiles with a + will see all projects, without the + will only see data of affected projects.
In your case it is more likely that your supervisor has access to "his projects", but is affected to no project. Adding the affectation should fix this issue.

2) You can't. Every day is defined with the same work period.

3) You're right.
An evolution is planned (#529) to be able to define a different profile/role on each project, but it is planned only on V3.8.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.069 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.