ProjeQtOr free project management software - [Solved] - No planning in reports for some project - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[Solved] - No planning in reports for some project

More
04 Nov 2013 14:18 - 21 Nov 2013 16:27 #1 by Drubs2010
Hello,

Why doesn't the planning reports, as monthly planning project/activity/resource, show any planned work? However, there are planned work in the Gantt.

regards,

Drubs2010.


Bonjour,

Pourquoi les états de planning, tel que Planning Projet/activités/Ressources, ne montrent pas le travail planifié? Pourtant, il y a du travail planifié sur l'état du Gantt.

Cordialement,

Drubs2010.
Last edit: 21 Nov 2013 16:27 by Drubs2010.

Please Connexion or Create an account to join the conversation.

More
04 Nov 2013 15:26 #2 by climb4fun
Hi Drubs,

in my report it shows planned work. Did you run planning? Planning figures are italic and colored different.

Regards,

Klaus

Please Connexion or Create an account to join the conversation.

More
04 Nov 2013 16:39 - 04 Nov 2013 17:01 #3 by Drubs2010
Thanks, that's it.

It's because I checked fix planning in the project. I unchecked it, but it wasn't enought, I had to run planning even if I did it before the check. Is that clear?


Conclusion : When we uncheck fix planning, we must run planning.

Regards,

Drubs2010.
Last edit: 04 Nov 2013 17:01 by Drubs2010.

Please Connexion or Create an account to join the conversation.

More
05 Nov 2013 17:12 #4 by climb4fun
Hi Drubs2010,

I'm really please I could help you. Just let me add to be excact:
  • If planning is fix, then no replanning will be done.
  • If you didn't run planning before fix the planning, then there will be no planning values - hence they are not displayed as plan value.
I hope this enlightens things.

Regards,

Klaus

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.