View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Activity is cut - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Activity is cut

More
21 Nov 2013 17:20 - 21 Nov 2013 17:20 #1 by Drubs2010
Activity is cut was created by Drubs2010
Hello,

In this exemple, some activity is cut.





Why "Reprise des fichiers" has charge on tuesday and thursday?

There is only one ressource at 70% on the project. The activity "Développement PGM transco" is the predecessor of "tests unitaires pgm transco".

Others, "Reprise" and "Modification CL", have no predecessor.

This is the planning:




Thank you for your help,

Drubs2010.
Attachments:
Last edit: 21 Nov 2013 17:20 by Drubs2010.

Please Connexion or Create an account to join the conversation.

More
22 Nov 2013 00:19 #2 by babynus
Replied by babynus on topic Activity is cut
Could you give information about priority of the activities ?
It they are all the same, then planning seems normal, priority if given by WBS.

So "Développement PGM transco" is planned =>OK
Then "Modification CL" is planned, but cannot start on the sale day because of predecessor constraint.
Then "tests unitaires pgm transco" is planned => OK
Then "Reprise des fichiers" is planned. And as it has no constraint, it used the availability left on tuesday.

If you want to avoid this behavior, you must allow your task "Modification CL" to start same day as predecessor : set delay to -1 in the dependency definition.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
22 Nov 2013 15:06 #3 by Drubs2010
Replied by Drubs2010 on topic Activity is cut
Thank you for this tip.

Regards,

Drubs2010.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.053 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.