View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Affectation percentage versus Assignment Rate versus Resources' FTE - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Affectation percentage versus Assignment Rate versus Resources' FTE

More
17 Déc 2013 23:32 #1 by alcassanti
Hi!

I've been banging my head against a wall for some time with Affectation percentage and Assignment rate and still can't figure out how they work (specially together).
I'll try my best to give you the picture of my situation so you can help me (or at least try :lol:) figure out how is the best way to do the planning.

I have a resource who will work in a project for 4 hours a day (half of his daily capacity) so, I set his affectation to 50%.
When I did the calculation of the project, the resource's workload was set for 8 hours a day for all activities where he was assigned.
That's not what I expected, so I changed the affectation back to 100% and set the assignment rate to 50%.
Another calculation and now the workload assigned was corrected on each activity, but there were always two activities running at the same time (and I understand why, but again, that's not what I expected).
So I returned to affectation and set it again to 50%... another calculation and no changes... still get 2 activities running at the same time, causing the daily workload of the resource to fill 8 hours instead of the 4 hours I wanted.
So I searched through the system and found FTE in the resource form. That solved the workload problem, but I can't keep the resource working 0,5 FTE for the eternity.

Any idea how to solve this in another way?

Thanks and regards!

ps.: planning mode "regular in half days" won't solve the problem, 'cause that's more resources planned on the same activity and they have no restriction of daily capacity.

Please Connexion or Create an account to join the conversation.

More
18 Déc 2013 09:38 #2 by babynus
Hi,
Affectation rate is calculated on a weekly basis. Tjis means, as you noticed, that resurce can work full days on the project. In fact it is the most frequent use case : resource affected to several projects will work several days on same project, trying to gather activities on eaxch project.

Assignment rate is the good way to plan half days for a resource.
Maybe you'll need to manage dependencies between tasks to avpid to plan full days for the resouce on same project. I think it is better than changing eesource capacity : you would not be able to plan resource on another project...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.129 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.