View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Modif ligne cout - Modif line expense - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Modif ligne cout - Modif line expense

More
01 Avr 2014 08:39 #1 by protion
Bonjour

File Attachment:


Je voudrais savoir quel fichier et ligne li faut modifier pour avoir dans le cout : Reste = validé - reel

Par avance merci


Hello

I would like to know which file and line li needs to change to have in the coC: Validated Rest - reel

Beforehand thank you

Please Connexion or Create an account to join the conversation.

More
01 Avr 2014 09:51 #2 by babynus

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
01 Avr 2014 11:10 #3 by protion
Mais cela est il possible pour le cout, car pour nous c'est de savoir ce qu'il reste une fois le travail fini, dont la différence entre l'assigné et le réel, le montant planifier et juste une information, qui en cas de dépassement (réel > assigné) et faux.

Comme dans l'exemple il y a plus de réel que d'assigné donc il ne devrais plus y avoir de reste


But it is it possible for the cost, because for us it is to know what there once remains finished job, difference of which enters the allocating and the real, sum to plan and just an information, that in case of overtaking (real> allocated) and falsehood.

As in example there is more real than allocating therefore it should no more have rest there

Please Connexion or Create an account to join the conversation.

More
01 Avr 2014 11:32 #4 by babynus
Once again, left cannot be negative.
Left cost = left work * resource cost.
Only thing that can tell you that work is finished is "left=0"
NEVER TRY AND PLAY WITH LEFT CALCULATION.
Left must be estimated by resource.
When left = 0, work is finished.

What you are expecting is gain : assigned - planned = assigned - (real + left).
When left=0 (work is finished), then gain = assigned - real

You can get an overview of what you expect : Expected progress = planned / validated

As in example there is more real than allocating therefore it should no more have rest there

If resource conciders there is some left work, then work IS NOT FINISHED !!!

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.048 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.