View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Planned start date - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Planned start date

More
21 Mai 2014 20:59 #1 by Hoss
Planned start date was created by Hoss
Hello,
I'm wondering if it is possible for the entire project timeline to shift to the left or right as appropriate when planned tasks are completed ahead of or behind schedule.
Thank you.

Please Connexion or Create an account to join the conversation.

More
21 Mai 2014 21:10 #2 by babynus
Replied by babynus on topic Planned start date
Recalculating planning will do this.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
23 Mai 2014 23:24 #3 by Hoss
Replied by Hoss on topic Planned start date
I am having difficulty having a follow on phase of a project shifting when a predecessor milestone is reached. Re-Calculating does not shift the project even though the milestone is 'done'. Am I missing a requirement? Please advise.

Please Connexion or Create an account to join the conversation.

More
24 Mai 2014 21:08 - 24 Mai 2014 21:09 #4 by babynus
Replied by babynus on topic Planned start date
"Reach" of milestone is not enough : it could be late (delayed).
You must set it to "done".
Then real end date will be automatically set and planning will take it into account.

Babynus
Administrator of ProjeQtOr web site
Last edit: 24 Mai 2014 21:09 by babynus.

Please Connexion or Create an account to join the conversation.

More
05 Jui 2014 21:35 #5 by Hoss
Replied by Hoss on topic Planned start date
I have a three phase project ongoing with up to 30 dependent tasks (activities) per phase. I have the project built so that the phases have completion milestones as predecessors to follow on phases. Even though all activities and the completion milestone have been set as done, the follow on phases have not/will not shift (left) to the earliest available date for earliest project completion upon recalculating planning. What am I missing? Please advise.

Hoss

Please Connexion or Create an account to join the conversation.

More
06 Jui 2014 16:30 #6 by babynus
Replied by babynus on topic Planned start date
Could you please post a screenshot ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.042 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.