View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Access rights and planned dates storage into requested/validated dates - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Access rights and planned dates storage into requested/validated dates

More
17 Déc 2014 17:08 #1 by jfg
Hello

I am working on planification of activities for project schedule.
I think I start to understand how it works and how to use it.
But I have noticed something which looks quite strange to me:

When a profile has rights to compute the planning, but no rights to modify existing activities (in my case: he can create and update his own activities, but not the others, and he has rights to compute the planning to have a gantt view), everything goes well.
If his activities have an impact on planning, delayed activities appears in red in gantt view.

But, he also has rights to store planned dates to requested/validated dates, and by this way he can modify elements of activities on which he has no rights.
For me, it is a problem, because the planning is delayed and there is no backup on initial requested/validated dates.
I think he should not be able to change requested/validated dates on activities he cannot update.

Do you think this behaviour is normal, or is it a bug or something in access rights?

Thank you very much.

Jean-François.
The topic has been locked.
More
17 Déc 2014 20:00 #2 by babynus
Hi,

Firs, your configuration seems strange : I never met a case where you can plan tasks you are not able to update.
This means you can change planned work for some tasks you are not able to change on other side (you cannot change assigned work for instance...)

In this schema, it should seem an issue to be able to change validated and requested dates for tasks not allowed to change.
But in fact, he should no also be able to change planned dates (and so plan) these tasks.

So issue or normal behavior : not sure.
In fact not planned use case ;)

Babynus
Administrator of ProjeQtOr web site
The topic has been locked.
More
17 Déc 2014 21:32 - 17 Déc 2014 21:32 #3 by jfg
Hi Babynus,

Thanks for your answer.

I understand this use case was not planned. In fact, it seems strange to me also.
But I see no alternative when a profile has rights to create and update his own elements.
The solution should be to forbid planning computation to this profile, but this is not satisfactory because his own activities will not be planned...

I agree with your remark: in fact, this profile should have no right to update planned dates on "read only" activities. But it works...

The aim of this configuration was to limit the number of activities created by project manager to macro-activities.
Then, members has rights to create sub-activities for each macro-activity for their own convenience.
Do you have an idea of a possible way to do this?

Jean-François
Last edit: 17 Déc 2014 21:32 by jfg.
The topic has been locked.
Moderators: babynusprotion
Time to create page: 0.039 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.