Hi everybody,
I'm trying to plan test session without success

(Working with 4.4.2)
I've set my products, different release for each product, then one test sessions for each release.
- Test session are aleready planed (there's nearly one version per month)
- each test session last 3 weeks
- generaly 3 persons are working on a test session
My goal is to have test session scheduled with their start/end dates
So I defined each test session like this :
- validated start date & validated end date
- 3 ressources assignments of 6 days at 30%
- a low priority (100)
- fixed duration
When I click on the "Plan" button, test session does not respect the validated start/end date

For example :
- Session 1 between 13/02 and 06/03/2015
- Session 2 between 13/03 and 03/04/2015
- Session 3 between 10/04 and 30/04/2015
They appear on the planning like this :
- Session 1 : planned start_date 13/02 -> planned end_date 26/05
- Session 2 : planned start_date 13/03 -> planned end_date 16/06
- Session 3 : planned start_date 10/04 -> planned end_date 18/06
the "planned start date" is ok (equals "validated start date"), but the can you explain me why the "planned end_date" is so far in the future and how to manage my planning to enforce them ?
Thank you