View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Planning estimation - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Planning estimation

More
26 Aoû 2015 15:32 #1 by papjul
Planning estimation was created by papjul
Hi,

How can we estimate planning?

Example:
I start a new project and I want to estimate how many days it will take and see its Gantt planning, without taking into account a particular person availability.

Even if I add validated work, if I don't assign someone to a task with a specific number of days, planning calculation go crazy by putting every tasks without assignment at today date (even if it doesn't respect dependencies).

Sorry if already asked, couldn't find keywords…

Thanks,

Please Connexion or Create an account to join the conversation.

More
27 Aoû 2015 18:41 #2 by babynus
Replied by babynus on topic Planning estimation
You can have several ways to solve your use case.

One (IMO the worst) is to defined your tasks as fixed duration tasks.
You can then have a good "draw" of your planning.

Another (my prefered) is to define a virtual resource with capacity = number of expected resources in the team.
Then you assign all the work to this resource : you'll then easily get a correct planning (or at least as correct as possible, as you don't take into account individual competencies). Another good point to thios method is that you can easily simulate adding a resourc e to the team : just change capacity of resource and plan again.
To get an even more realistic planning, you can apply this mtehod with several resources, on for each functions. For instance, if your team will be 1 project leader, 2 analysts and 4 developer, just create 3 resources : PL (capacity 1), ANALYT (capacity 2) and DEV (capacity 4).

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.044 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.