ProjeQtOr free project management software - Différence between "charge" and "durée" - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Différence between "charge" and "durée"

More
19 Oct 2015 13:30 #1 by El Wallos
Hi all,

I have a doubt when I create a task, I don't understand the difference between "charge" and "durée"? In which case I need to use each one?

PD: I know the difference between "charge" and "délai" but not between "charge" and "durée"

Thanks for sharing your knowledge.

Martin
The following user(s) said Thank You: chenevieredd

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 14:24 #2 by babynus
"Charge" (work) is quantitiy of Work.
"Durée" (duration) is delay, in open days.

If 2 resources share 20 days of work (charge) to do on a task, with equal repartition (10 days each), duration (durée) will be 10 days, and delay will be 2 weeks (14 days or 12 days if task starts on monday).

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: El Wallos

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 14:47 #3 by El Wallos
Thanks for reply.

If I work with ASAP planification method, I just fill "durée" field and it is enough.

So, in which case can I use "charge"?

Martin

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 15:07 #4 by babynus

If I work with ASAP planification method, I just fill "durée" field and it is enough.

NO.
Duration is informative unless you choose "fixed duration" planning mode for the task.

So, in which case can I use "charge"?

ALWAYS
You should always define work as ProjeQtOr is work driven : planning is calculated from work data, and not from duration. It is the only way to have realistic planning.
Imagine you have a resource working 3 days on Task A and 2 days on tasks B, and tasks don't have a dependency (resource can work indenpendently on any task). If you work with duration, global duration of the project is 3 days (the longest duration). But if you work on work, total duration of project is 5 days.
This is a simple example, but imagine working with 50 resources, working on 100 tasks, some with dependencies, some not, and some resources sharing some tasks, .... Working with duration will not help. Working with work will compute realistic planning.

Moreover if you have 2 tasks, each with duration of 5 days, task A is complete, task B half completed (50%). What is global progress of project ?
You should say 75% (50% for task A, 25% for task B).
But now if I say that task A is a 0,1 day per day task (some management for instance) and task B is full time for 2 resources, real progress is 52% = (0.5+5)/10.5.
And if resource estimate that they need 4 extra work days to end task B (reestimate left work), then progress is just 38% = (0.5+5)/14.5

It is work driven (also called effort driven) planning.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: El Wallos

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 16:26 #5 by El Wallos
It takes sense but when I update the new value on "charge" field (ex: 7 days) without fill "durée" (with ASAP planification), the Grantt project doesn't update the Gantt planing as I expect (a task with 9 days with the week end).

Do you have any documentation with a case study? Just to do it step by step and understand better how your software works?

Thanks.
Attachments:

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 16:48 #6 by babynus
Just because you did not run planning calculation : planning is not automatically calculated as it is considered as a management act.
Use button on top left of planning view (with the 2 gears)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.056 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.