ProjeQtOr free project management software - Différence between "charge" and "durée" - Page 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

Différence between "charge" and "durée"

More
19 Oct 2015 16:59 #7 by El Wallos
I clicked on this button before send you the screenshot to generate the plan.

I click again and the result is the same. Any explication?

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 17:29 #8 by babynus
Because you just defined the Validated work, which is just a reference (informative data to define margin, no effect on planning)
You have to add work through "assignment" (list with "add" button)
Notice that projector plan "left work" : you have no left work ,so nothing is planned.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 17:46 #9 by El Wallos
It doesn't work, I attach the Gantt and the detail of activity.
Attachments:

Please Connexion or Create an account to join the conversation.

More
19 Oct 2015 18:04 #10 by babynus
Define some left work in your assignment. It is zero, so not planned.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
20 Oct 2015 09:30 #11 by El Wallos
You are a "Master", thanks a lot.

Just to be sure, I assigned the work with the "change button" (pen) directly on the activity details on the Assignement tab, is it the best practise or it exists a better practise?

Please Connexion or Create an account to join the conversation.

More
20 Oct 2015 09:49 #12 by babynus
it is the best practice for the Project Leader.
(well, in fact you should define assigned and left work while Creating the assignment).

What is important, it is that each project member will re-evaluate left work reguliarly (at least once a week) and update it in the Real Work Allocation (imputations) screen.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: El Wallos

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.038 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.