View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] Teams are not working at fully time on project 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Teams are not working at fully time on project 2

More
26 Oct 2015 17:09 #1 by El Wallos

babynus wrote:

One question more, my team is working on "real projects" and "run projects" (activities from day to day), so if I want to plan some projects and my "run projects", what is your recommendation to plan it on ProjeQtOr? because "run projects" is a task that is cyclic but I don't know how to add it on ProjeQtOr (which planning uses ... etc)

Use the "regular between dates" planning mode. It's done for this.
You define start and end dates (for instance 01/01 => 31/12) and assign resource with expected work for the period. Planning will reserve work, reguliarly.
You can also opt for "in half days" or "in full days" if you don't work to book 0,1 day par day.


Ok, I'm trying to use "regular between dates" planning mode and it is worked for plan but what do you fill in "assign work" if the task is planned for 1 year and I have more than 1 ressource assign to this task?

Please Connexion or Create an account to join the conversation.

More
26 Oct 2015 17:12 #2 by babynus

Ok, I'm trying to use "regular between dates" planning mode and it is worked for plan but what do you fill in "assign work" if the task is planned for 1 year and I have more than 1 ressource assign to this task?

Exactly what you expect.
If you expect 3 resources will work half time on the task, you can assign 110 days (half a year) to each resource on same task.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Oct 2015 17:17 #3 by El Wallos
Ok, so if I have 7 people with each person is working 35% per day on this cyclic task, the formule is:

365 * 0.35 /7 = 18.25 days

(total time * rate assign to the project) / number of ressource, is it correct?

Please Connexion or Create an account to join the conversation.

More
26 Oct 2015 17:25 #4 by babynus
no !
First a year is not 365 days (in a workly basis) but about 220 (must exclude week-ends, off days, holidays).

Then if eauc is 35% on the task, then each has 220 * 0.35 = 77 days on the task
And total assigned work on the task is 77 * 7 = 537 days.
(this is not Prject Management, just arythmetics)

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
26 Oct 2015 17:35 #5 by El Wallos

babynus wrote: no !
First a year is not 365 days (in a workly basis) but about 220 (must exclude week-ends, off days, holidays).

Then if eauc is 35% on the task, then each has 220 * 0.35 = 77 days on the task
And total assigned work on the task is 77 * 7 = 537 days.
(this is not Prject Management, just arythmetics)


Ok for 220 days, it was just an example but you are right.

For arythmetics, you are "double" right, :blush: but I prefer to be sure that's why I'm asking :blink:

One month later, one person is added to this team, I need to change the charge for person on the team, is it right?

Please Connexion or Create an account to join the conversation.

More
26 Oct 2015 17:41 #6 by babynus

One month later, one person is added to this team, I need to change the charge for person on the team, is it right?

All depends ...
Do you add one resource because task is more important that planned : the new resource is in addition,
or do you add resource so that other resources are less busy on this task (to do other things), then yes you must change left work on each resource.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: El Wallos

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.045 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.