ProjeQtOr free project management software - [SOLVED] Teams are not working at fully time on project 3 - Page 2 - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Teams are not working at fully time on project 3

More
27 Oct 2015 18:06 #7 by El Wallos
so, if I have my configuration in my test case is:

33% Project 1 ---> "regular between dates" ---> cyclic tasks
33% Projet 2 ---> "reguler between dates" ---> cyclic tasks
33% Projet in general ---> ASAP

What is your recommendation/configuration using "regular plan" for my test case?

Because if I keep 100% in my activity assigment with "regular", I think my Real Work Allocation should not be right with my expectation (33% suggests every day for my two cyclics tasks)

Please Connexion or Create an account to join the conversation.

More
27 Oct 2015 18:10 #8 by babynus
Just try.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
28 Oct 2015 09:26 #9 by El Wallos
Thanks a lot Babynus, you are right. :woohoo:

It is easier than with change the different rates!!!

But I'm not sure why it is correct? it is because the assigned work was multiple by the rate to calculate the assigned work?

Please Connexion or Create an account to join the conversation.

More
28 Oct 2015 09:28 #10 by El Wallos
And it isn't depend to the number of assigned ressources... it is better. :evil:

Please Connexion or Create an account to join the conversation.

More
28 Oct 2015 12:23 #11 by babynus

it is because the assigned work was multiple by the rate to calculate the assigned work?

Yes

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: El Wallos

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.040 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.