ProjeQtOr free project management software - Plan to a specific date - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Plan to a specific date

More
05 Jan 2016 17:17 #1 by El Wallos
Hi

I plan project for IT System, and sometimes, we need a specific date for some tasks (i.e., a window maintenance...) but I didn't simulate it on ProjeQtOr, is it possible to force a task to a specific date?

Thanks

Please Connexion or Create an account to join the conversation.

More
05 Jan 2016 17:22 #2 by babynus
Replied by babynus on topic Plan to a specific date
You have several ways :
- planning mode = not start before, and hight priority (1)
- planning mode = regular between dates (will have highest priority) => my advise
- set a fixed milestone and add task with only milestone as predecessor, with plannong mode = fixed duration
- define task as a Meeting => also a very good alternative

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
06 Jan 2016 10:01 #3 by El Wallos
Replied by El Wallos on topic Plan to a specific date
Thanks for your quick answer. In my case, I have two projects with planning mode "regular between two dates", and in this case, just the last solution worked for me.

As a suggestion, I think a new planification mode could be create to avoid to change the priority and/or the planification mode to force a date to a task, are you plan this on your road map?

Thanks again.

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 14:12 #4 by El Wallos
Replied by El Wallos on topic Plan to a specific date
Hi Babynus, do you think it is a possible evolution?

Please Connexion or Create an account to join the conversation.

More
11 Jan 2016 15:08 #5 by babynus
Replied by babynus on topic Plan to a specific date
I'm afraid this planning mode will not be possible.
Imagine you define a "fixed" tasks on 1 day with 2 work days ...
Or you fix the task, and assign it to a resource who is out this day ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
12 Jan 2016 12:46 #6 by El Wallos
Replied by El Wallos on topic Plan to a specific date
You are right but in the real world, sometimes we need plan to a specific date that's why in ProjeQtOr, some plannings cannot reproduce the reality. Nothing can be done now.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.058 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.