ProjeQtOr free project management software - Failed to schedule an activity whereas ressource fully available - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Failed to schedule an activity whereas ressource fully available

More
08 Jui 2016 12:21 #1 by mvern
Hello,
I have someone who work on a project "P1" at 100%.
This person have a training for 1.5 days during this project "P1".
Training activity have a higher priority than tasks on P1.
My problem is that I have a message when trying to calculate the planning for the "training" project, saying that activity can't be scheduled.
Indeed this person is planned to work on a tasks on P1 but what I don't understand is that this tasks can start before "training" activity and end after. It seems that planning calculation tool can not interrupt a task for some day to allow another one to be inserted ???
What have I done wrong ?








Thx
Attachments:

Please Connexion or Create an account to join the conversation.

More
08 Jui 2016 22:51 #2 by babynus
Check affectation of resource "Michel" ro project "Formation".
Maybe start or end date of affectation (I would bet on end date before 06/06) forbids planning at the expected date.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
09 Jui 2016 09:28 #3 by mvern
Hi Babynus,
unfortunately it does not seem to be this point, Michel is assigned to "formation" between 06 to 07, see below. What am I missing ?
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Jui 2016 11:29 #4 by babynus
Can you have some tests on affectations :
- remove end date, replan : what is the result ?
- remove start and end date, replan : what is the result ?

Could you also post result of report "Monthly Planning per Resource/Project/Activity" showing planning for Michel ?

THX

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
09 Jui 2016 11:51 #5 by mvern
I made tests on affectations, ie remove end date for "formation" project (no start or end date on other porject), and now the task is planned but it's not what I want to plan as "formation" is at fixed date (06/07 to 07/07), I want that other task on project "etude carte" start before this "formation" and remaining work end after "fromation".
See below "monthly planning for michel " before test:
Attachments:

Please Connexion or Create an account to join the conversation.

More
09 Jui 2016 17:01 #6 by babynus
Hi,
It' because your tack has no "high" priority.
For instance, if you change planning mode to regular between dates, planning will be better.

But for these kind of "fixed" work, try and directly input real work (in the future). It is the best way to "fix" some work.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.070 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.