Hi,
For sure I was not clear

, in fact I have 2 points:
- first one is on some tasks with no more time available for one ressource that is not displayed in "planning by ressource", see below (I expect them to be displayed in purple, right ?):
- 2nd point is more e request :
on some tasks correctly displayed in purple, I would like to see the "not plannified work" because of some conflicts in report such as "synthesis of availability. Currently I have info in each activity and would like to have it in a workload sheet.
When I have availability = 0, it could mean that all is planned and OK, but also mean many activities have been correctly planned but some are not because ressource is already full.
Maybe future activity not fully planned could be displayed as some extra work in the past.
A kind of mix of this :
into this :
moreover activity "integration", "campagne d'essai" and "spec du logiciel" are not listed in this workload for Jean whereas he is assigned to ... From my point of view we're missing some interesting info in this workload then.