ProjeQtOr free project management software - [SOLVED] Activity starts before milestone - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

13 mai 2025 (10h30-12h)

5 juin 2025 (16h-17h30)

 
 

Planifiez avec ProjeQtOr

14 et 15 mai 2025 (9h-12h30)

18 et 19 juin 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai (9h-12h30)

25 et 26 juin (9h-12h30)

 

 

 

[SOLVED] Activity starts before milestone

More
04 Sep 2016 12:27 #1 by FGAIL87
Hello,
I have a problem of understanding on the use of milestones.

I want an activity begins after milestone (milestone = hardware delivery, activity = hardware configuration).
If I set a milestone and a successor activity, there is no problem in the schedule.
After, if I assign a resource to the activity, it starts before the milestone (the current day). The planning activity is configured as "as soon as possible".

Is it normal ?

Please Connexion or Create an account to join the conversation.

More
04 Sep 2016 12:44 #2 by babynus
We would need more details to understand.
But as you describe use case, I guess you just did not run planning calculation...

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Sep 2016 13:07 #3 by FGAIL87
No precisely, is after calculating planning that the problem happens.

Here, the planning before assigning the work.


And there, the planning after assigning work and calculated planning.


Only the fixed milestone, has a valid date.
Activities have working duration in hours.
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Sep 2016 13:35 #4 by babynus
Can you please show detail of first task "Configuration Windows", with details of assignments.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
04 Sep 2016 14:20 #5 by FGAIL87
The detail of first task



Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Sep 2016 15:51 #6 by babynus
Strange, all seems correct, and I can confirm that correct result is exactly what you expect ... and what I get.


What is the project type of your projects ? (Configuration PC and its parent)
Can you try and create dependency from milstone to sub-project "Configuration PC" ? What is the result ?

Babynus
Administrator of ProjeQtOr web site
Attachments:

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.105 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.