It is by default calculated from assigned - real but the calculation result can be overriden by an ad-hoc value. My understanding is that it does not reset to default "calculated from assigned - real" behavior again if it is once overriden (Am I right?
)
In fact, left is defined as assigned when assigned is defined.
Then each time real is entered it is substracted from left.
So when left is changed, new real is substracted from new left.
Also, is assigned is changed, differnece is added to left.
But this is not linked to the tool, it is Project Management basis.
Also, it is not editable when the activity is in status done
I don't think there is such constraint.
Only contraint I know is that you cannot close an activity with left work...
In the manual, I think an example or describing the use case and the behavior would make it clearer to the reader.
But this is not a specificity of the tool.
Most PM Tolls work this way...
So if you know PM, it is really clear, I think.
Left work is rarely entered in estimation step as the project manager knows only the needed workload and enters it in the assigned field
And then lefdt work is exactly equal to assigned work