View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - [SOLVED] RealWork allocation update - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] RealWork allocation update

More
03 Oct 2016 18:21 #1 by bourle
Hi

I have a question on the "Realwork allocation".
When I add and save value in realwork allocation, there are no update in the last line "total". But it's working in your demo. I don't find the parameter.
And a "ticket" don't add time on "planning activity". The time is add on the "parent activity" (red in screenshot) of the "planning activity" (green in screenshot).

Thank you.
Attachments:

Please Connexion or Create an account to join the conversation.

More
04 Oct 2016 18:39 #2 by babynus
Replied by babynus on topic RealWork allocation update

When I add and save value in realwork allocation, there are no update in the last line "total". But it's working in your demo. I don't find the parameter.

You must be sure to be in V5.5.2 and clear the browser cache.

And a "ticket" don't add time on "planning activity". The time is add on the "parent activity" (red in screenshot) of the "planning activity" (green in screenshot).

Yes, it is designed this way. Only real work on ticket is summed up to the activity.
This is done to be able to enter extra work directly on the activity, and be able to reduce value without setting a mess in real work of tickets.

Babynus
Administrator of ProjeQtOr web site
The following user(s) said Thank You: bourle

Please Connexion or Create an account to join the conversation.

More
05 Oct 2016 11:38 #3 by bourle
Replied by bourle on topic RealWork allocation update
Ok. thx. I'm in v5.5.1

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.029 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.