View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - Monthly, Quarterly reports, exports - Page 2 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Monthly, Quarterly reports, exports

More
14 Oct 2016 11:54 #7 by andresch
Hi, Sorry been away on project business.

The milestones contain detailed activities:
What I mean with this. We link an activity(s) to a milestone. Milestone is the Parent and the activities are the children (detail tasks to achieve the Milestone.Because the milestones are the contracted deliverable, we therefore have the ability by linking the activities to the milestones to see the detail activities and be able to report as per the contract. By looking at the sample Excel spreadsheet . Some Activities are linked to a milestone and some not. What we then what to do is to allow the export of the Activities and related information as per the sample spreadsheet. One comment I want to make. The last column is labeled MRP notes (on the sample Spreadsheet). The intention is to get the client Project Manager to review all completed activities and then comment. We want to list their comments as well to make sure all team members address their comments in the Results field. The Results field is used as the complete narrative on what what was done and how the activity met the initial requirement.

I hope this helps.
Could you review this and sent me a quote for this.
Attachments:

Please Connexion or Create an account to join the conversation.

More
14 Oct 2016 17:26 #8 by babynus
Hi,

It's a vocabulary issue : in project management a milestone cannot contain activities, it is just a key date.
So what you call a Milstone is a Phase, regrouping activities, and possibly ending with a milstone (delivery date)
So this is possible.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.