View ProjeQtOr On SourceForge.net
ProjeQtOr - Project Management Tool
Supportez nous sur Capterra
OIN - Open Invention Network
ProjeQtOr free project management software - How to know "how many working time" is still free by ressource ? - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

How to know "how many working time" is still free by ressource ?

More
22 Déc 2016 12:20 #1 by noisette
Dear all,
I would like to know if is it possible to know "how many working time" is still free by ressource ?
I explain : we have 4 projects. We want to know if we have enough ressources (humain, mainly) to start a new project.
Where I can't find this information ?
Thanks a lot for your help and for the real good open source software
All the best
Christophe Noisette

Please Connexion or Create an account to join the conversation.

More
22 Déc 2016 12:24 #2 by babynus
Follow-up > Reports > Resource availability

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
22 Déc 2016 13:44 #3 by noisette
Thanks, I found the function.
I can't understand something : we have a meeting in January, 9th (duration : 7,5 hours) (cf. attachment 1738)
In the meeting's detailed form, I could read that for LV (but for every body) has 0,99 h of time non planned. But, in the form "Resource availability " I can see the LV has a lot of available time (attachment 1739).
So the datas seem not comptatible, no?

All the best
Christophe
Attachments:

Please Connexion or Create an account to join the conversation.

More
22 Déc 2016 13:48 #4 by babynus
On the assignment, "not planned work" means that resource has not enough avaailability "on the meeting date".
Meetings have specific planning mode : date is fixed.

But some uncompleetness of the availability is to be concidered...

Please check Real Work allocation for the resource on meeting date and if issue is confirmed, please report.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
22 Déc 2016 14:52 #5 by noisette
Thanks again.
I don't understand the last sentence : "Real Work allocation for the resource on meeting date and if issue is confirmed, please report.
Could you be more precise?
Christophe

Please Connexion or Create an account to join the conversation.

More
22 Déc 2016 20:19 #6 by babynus

I don't understand the last sentence : "Real Work allocation for the resource on meeting date and if issue is confirmed, please report.

Go to real work allocation, select Resource LV, go to week corresponding to meeting date, check "show planned work" and see what is planned (or real) for resource on meeting date.
If nothing is planned (connect as admin to be sure you see all data) nor real, this seem to be an issue.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.063 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.