ProjeQtOr free project management software - Saturday and Sunday become work days when migrating database to 6.0.5 - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

Saturday and Sunday become work days when migrating database to 6.0.5

More
09 Jan 2017 19:03 #1 by phil-bzh
Hello

I wish you an happy new year :-)

I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.

My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?

In environmental parameters / diary, I have one diary called "default" where I had written the other days off (public holidays = "jours fériés"). I could do the same with satursdays and sundays, for the 2 years of my project but it's a bit boring ;-)

Thank you for your help.


PS : thank for having added in the new version the report I suggested "work plan per month and per resource" (that is where I found my resources work all days of the month ;-) )

Please Connexion or Create an account to join the conversation.

More
09 Jan 2017 21:13 #2 by babynus

I migrated to ProjeQtOr v6.0.5, from a database version v5.4.5 (yes, a bit old...). There weare 46 errors / warnings.

Please post log file here.

My project seems good but satursdays and sundays are now work days : could you tell me how to get them simply back to days off as they were before the migration ?

This can be changed in Global Parameters.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
10 Jan 2017 12:29 #3 by phil-bzh
Hello,
Thank you for the information on days off in Global Parameters.
I join the log.
Sincerely.

File Attachment:

File Name: projeqtor_..._bis.txt
File Size:66 KB
Attachments:

Please Connexion or Create an account to join the conversation.

More
10 Jan 2017 22:48 #4 by babynus
Hi,

It looks like you upgraded twice up to V5.5.2....
Nothing blocking, all should work fine.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Jan 2017 17:11 #5 by phil-bzh
Thank you for looking at the log. I don't know how I did that but it's possible ;-)
I confirm all seems ok, once satursdays and sundays made days off again.

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.049 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.