ProjeQtOr free project management software - [SOLVED] S curve Planned value not egual to project estimates - ProjeQtOr

Prochaines sessions de formation

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)

Mardi 23 avril (10h30-12h)

Jeudi 16 mai (16h-17h30)

Jeudi 13 juin (10h30-12h)

 
 

Planifiez avec ProjeQtOr

3 et 4 avril (9h - 12h30)

 
 

Administrez avec ProjeQtOr

10 et 11 avril (9h - 12h30)

 

 

 
 

[SOLVED] S curve Planned value not egual to project estimates

More
11 Fév 2017 15:56 #1 by mcambron@videotron.ca
Hello,
I have a mini project with about 10 task and 207 assigned hours ( seee screen capture) and when i produce the S curve , I see only 29 hours for the coût budgetiser du travail planifié (see s curve figure). Shouldn`t the 207 assigned hours be equal to the planned value ( coût budgetiser du travail planifié)? Am I missing something?
Regards
Thanks
Attachments:

Please Connexion or Create an account to join the conversation.

More
11 Fév 2017 16:39 #2 by babynus
Mayby a conversion issue.
It seems S-curve is displayed in days but unit displays "h" for hours.
Can you confirm that it is correct if unit is not jours but days ?

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
11 Fév 2017 16:58 #3 by mcambron@videotron.ca
Hello,
It does not seem to be a conversion issue since 207 assigned hours represents 25.8 days of effort ( at 8 hours per day) and the S curve displays 30 hours of planned work.
Would you have any suggestions?
Regrads
Thank for your support

Please Connexion or Create an account to join the conversation.

More
12 Fév 2017 18:26 #4 by mcambron@videotron.ca
To complement the issue, the hours on burn down chart seem to be correct.
Regards
Michel

Please Connexion or Create an account to join the conversation.

More
20 Fév 2017 15:39 #5 by mcambron@videotron.ca
Hello Babynus,
Have you had the time to investigate the problem? I have added notes to my discussion on the forum and I am not shure you have received them.
Thank you in advance for your support
Regards

Please Connexion or Create an account to join the conversation.

More
24 Fév 2017 21:06 #6 by babynus
Hi,

Issue is fixed on V6.1.1,
and it is (as I guessed) a conversion issue : days were displayed with unit showing hours

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.036 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.