ProjeQtOr free project management software - [SOLVED] Kanban column - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

5 juin 2025 (16h-17h30)

19 juin 2025 (16h-17h30)

9 septembre 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

18 et 19 juin 2025 (9h-12h30)

17 et 18 septembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai 2025 (9h-12h30)

25 et 26 juin 2025 (9h-12h30)

24 et 25 septembre 2025 (9h-12h30)

 

 

 

[SOLVED] Kanban column

More
05 Mai 2017 09:32 #1 by mtrem
Kanban column was created by mtrem
Hello
i bought kanban module, and i have some question.
1- how order column is defined ? because in my case is not correct , i think it's link on workflow, no ?
2 -when i change column for an activity (drag un drop) change status automaticaly ?
Thanks
how
Attachments:

Please Connexion or Create an account to join the conversation.

More
05 Mai 2017 10:14 #2 by babynus
Replied by babynus on topic Kanban column
Hi,

1) For Kanban per Status, order of columns is order of status (defined in the Status List of Values).
NB : this order will also have impact on workflow

2) Yes, moving to a column (that may be relative to several status) item moves to first status for the column.
NB : This is for status based Kanban, for a Kanban per Version, version is changed

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
05 Mai 2017 10:24 #3 by mtrem
Replied by mtrem on topic Kanban column
Ok i 'll check why it's not good for me.

another ask. in activity is set the estimate charge
but in kanban i have 0.
Attachments:

Please Connexion or Create an account to join the conversation.

More
05 Mai 2017 10:54 #4 by babynus
Replied by babynus on topic Kanban column
"Estimate" is not really a field in Actrivity. It is valid only for tickets.
But you're right, it should be set to "reassessed" or "validated".
We'll fix this on next version of Kanban.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.067 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.