ProjeQtOr free project management software - Following tasks could not be completely planned - ProjeQtOr

Prochaines Sessions

Les prochaines formations et démonstrations sont ouvertes, inscrivez-vous rapidement !

 

Démonstration de ProjeQtOr

(gratuit, sur inscription)
 

5 juin 2025 (16h-17h30)

19 juin 2025 (16h-17h30)

9 septembre 2025 (10h30-12h)

 
 

Planifiez avec ProjeQtOr

18 et 19 juin 2025 (9h-12h30)

17 et 18 septembre 2025 (9h-12h30)

 
 

Administrez avec ProjeQtOr

20 et 21 mai 2025 (9h-12h30)

25 et 26 juin 2025 (9h-12h30)

24 et 25 septembre 2025 (9h-12h30)

 

 

 

Following tasks could not be completely planned

More
23 Mai 2017 17:39 #1 by #Chris
Hello all,

I have a problem if I assign ressources to Meetings. If I run the planning I always get the follwing pop-up Following tasks could not be completely planned
See also the attached pic.
If I do this with an activity on the same ressources it is no problem and the planning runs fine. Also on the same day there is no other activity, etc for that ressources
So I do not know what I am missing.

Any help is very much appreciated :)
Attachments:

Please Connexion or Create an account to join the conversation.

More
23 Mai 2017 21:01 #2 by babynus
Check reports in category "planning" : some will show you planned work day by day for the resource, so you may find some unexpected planned work for the resource.

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

More
24 Mai 2017 22:26 #3 by #Chris
ok I found the issue.
I have the following structure:

Main project (administrative)
|- Subproject (administrative)
| - sub-sub-project (internal project)

I assigned my ressources to the main project, but with 0% rate.
So even if I assigned 100% to the internal sub-sub-project , it seems to be that the available rate follows that of the main project, which is zero.

If I now set the rate in the main project to 100% it is ok...
But it is also ok if I remove my ressources from the main project, so that they are only assigned to the sub-sub-project.

So long explanation but the question is now, if this behaviour is intentionally and is as follows:

Assume that
the ressource is assigned to the main project with e.g. to rate 100%, then to the sub-project 50%, then to the sub-sub-project also to 50% --> Is the maximum rate of the sub-subproject now effective 25%?
Did I get this right?

Thanky you very much

Please Connexion or Create an account to join the conversation.

More
25 Mai 2017 17:43 #4 by babynus
Not exactly.
Allocation rates do not multiplicate.
They are limits.
So the smallest will be the constraint.
A1 => 100%
A1.1 => 50%
A1.1.1 => 50%
then limit on A1.1.1 is 50%
A1 => 50%
A1.1 => 100%
A1.1.1 => 100%
then limit on A1.1.1 is also 50%

Babynus
Administrator of ProjeQtOr web site

Please Connexion or Create an account to join the conversation.

Moderators: babynusprotion
Time to create page: 0.043 seconds

Paramétrages de cookies

×

Cookies fonctionnels

Ce site utilise des cookies pour assurer son bon fonctionnement et ne peuvent pas être désactivés de nos systèmes. Nous ne les utilisons pas à des fins publicitaires. Si ces cookies sont bloqués, certaines parties du site ne pourront pas fonctionner.

Session

Veuillez vous connecter pour voir vos activités!

Autres cookies

Ce site web utilise un certain nombre de cookies pour gérer, par exemple, les sessions utilisateurs.